Contractual penalties and damages in commercial contracts: the 8% cap, conditions for claiming damages, late-payment interest, exemptions and how to draft clauses you can enforce
Translated from the Vietnamese original. If the versions differ, the Vietnamese text prevails.
Many contracts set very high penalties, yet in a dispute the court or arbitral tribunal accepts only a small part. The reason usually lies in how the Commercial Law 2005 governs the two main remedies, and in the differences between the Commercial Law and the Civil Code 2015. This article explains each remedy with worked examples and suggests how to draft the clauses. It ends with a note on the draft amendment to the Commercial Law now before the National Assembly.
Which law applies
A contract where at least one party is a trader and which aims at profit is usually a commercial contract governed by the Commercial Law; matters the Commercial Law does not cover fall under the Civil Code. Contracts not aimed at profit, such as those between a company and an individual tourist, are mainly governed by the Civil Code and the Consumer Protection Law. Identifying the right law comes first, because the two laws differ on penalty amounts and on combining penalties with damages.
Penalties: must be agreed, capped at 8%
- A penalty applies only if the contract provides for it (Article 300 of the Commercial Law).
- The penalty for a breach, or the total for several breaches, may not exceed 8% of the value of the breached part of the obligation, except for inspection services (Article 301).
- The 8% is calculated on the breached part of the obligation, not the total contract value.
Illustration: this is an illustrative example. A VND 1 billion sale contract is delivered in 4 instalments of VND 250 million. The seller delivers the third instalment late. The breached obligation is VND 250 million, so the maximum penalty is VND 20 million, even if the contract says "10% of the contract value". The part above 8% is not enforceable.
For civil contracts, Article 418(2) of the Civil Code lets the parties agree the penalty freely, with no cap, unless another law provides otherwise.
Damages: must be proven
Under Article 302, damages cover the actual, direct loss suffered and the direct profit that would have been earned but for the breach. Under Articles 303 and 304, the claimant must prove three elements: a breach of contract, actual loss, and that the breach directly caused the loss. The injured party must also take reasonable steps to mitigate; otherwise the breaching party may reduce damages accordingly (Article 305).
In practice the hardest part is proving the "direct profit that would have been earned". Keep evidence: contracts with your own customers cancelled because of the partner's delay, invoices for replacement suppliers, and breach notices.
Can you claim both penalty and damages?
Under Article 307 of the Commercial Law, without a penalty clause only damages may be claimed; with a penalty clause, both penalty and damages may be applied. The Civil Code takes the opposite approach: if only a penalty is agreed without agreeing to combine penalty and damages, the breaching party pays only the penalty (Article 418(3)). So the contract should state expressly that the injured party may apply both remedies, regardless of which law the court applies.
Late payment
When payment is late, the injured party may claim interest on the overdue amount at the average market overdue interest rate at the time of payment, for the period of delay, unless otherwise agreed or provided by law (Article 306). The "market average" is often disputed in court, so the contract should state a specific rate, for example a percentage per year on the overdue amount. Late-payment interest is separate and does not count towards the 8% penalty cap.
Exemptions from liability
Under Article 294, the breaching party is exempt when:
- an exemption agreed by the parties occurs;
- a force majeure event occurs;
- the breach is entirely the other party's fault;
- it results from a decision of a competent state authority that the parties could not have known when contracting.
The breaching party must prove the exemption and notify the other party in writing immediately (Article 295). A force majeure clause should list specific events, the notice duty and deadline, and the right to terminate if the event lasts too long.
Drafting tips
- Set a penalty for each type of breach (late delivery, short delivery, quality, late payment), not exceeding 8% of the breached obligation for commercial contracts.
- State expressly that penalty and damages may be applied together.
- Agree late-payment interest as a specific figure.
- Cap total liability if you are the service provider, but note that with consumer customers, exclusion and limitation clauses risk being ineffective under the Consumer Protection Law.
- Set out a breach notice procedure and cure period before remedies apply.
The draft amendment to the Commercial Law
The bill amending the Commercial Law and related laws, submitted to the second session of the 16th National Assembly, proposes repealing the Commercial Law's provisions on contracts and Chapter VII on remedies from 1 January 2028. If passed, the 8% cap would disappear and the Civil Code would apply to commercial contracts too. This is a draft; long-term contracts should include a change-in-law clause. See our separate article on the draft.
Quick answers
How will a court treat a 12% penalty? For a commercial contract, the part above 8% of the breached obligation is not enforced; the part within the cap remains valid.
Does a deposit count towards the 8% cap? A deposit is a security measure under the Civil Code, different from a penalty; see our separate article on deposits and the new guidance of the Judicial Council.
Legal basis: Commercial Law 2005 (Articles 294, 295 and 300 to 307); Civil Code 2015 (Article 418); Consumer Protection Law 2023; bill amending the Commercial Law and related laws.
This article is general information and does not replace advice on your specific case.