Project land left idle: current rules under the Land Law 2024, the draft amended Land Law with a progressive charge and recovery after 60 months, a proposed 0.2% land use tax and what investors should do now
Translated from the Vietnamese original. If the versions differ, the Vietnamese text prevails.
Two drafts before the National Assembly at its Second Session both target idle project land: the draft Land Law (amended), debated in plenary on the morning of 29 October 2026 and expected to be considered for passage at this session together with the Housing Law and the Law on Real Estate Business; and the draft law amending the Corporate Income Tax Law, the Law on Non-Agricultural Land Use Tax and the Personal Income Tax Law, submitted on 23 October 2026. Neither has been passed. For investors with allocated or leased project land that is behind schedule, now is the time to review their files, as the cost of delay may rise significantly.
Current rules
Under Article 81(8) of the Land Law 2024, where land allocated or leased by the State for an investment project is not used for 12 consecutive months, or is 24 months behind the project schedule, the investor may be granted an extension of up to 24 months and must pay the State an amount equal to the land use fee or rent for the extension period. If the land is still not used when the extension ends, the State recovers it without compensation for the land and assets attached to it, except in cases of force majeure. According to some agencies' comments, the current calculation effectively allows delays of about 48 months before recovery.
The draft Land Law (amended)
- Investors leaving land unused or slow to use must pay an annual progressive charge that rises with the length of the violation, replacing the payment for the extension period.
- If the land is still not put to use after more than 60 months, the State recovers it.
- Land use and investment progress on earlier projects becomes a basis for considering land allocation or lease for the same investor's new projects.
- Specific land pricing and land valuation consultants are abolished; land use fees and rent are calculated using land price tables and adjustment coefficients.
- How violations are identified, time limits, conditions and the method for calculating the progressive charge will be set by a guiding decree.
The Ministry of Agriculture and Environment explains that the 60-month mark implements Resolution 21-NQ/TW of 28 July 2026, which calls for higher taxes on idle land, and that current law does not clearly define "not putting land into use" or "behind schedule". Some agencies proposed separate time limits for projects that do not use land and those that use it slowly.
The proposed 0.2% tax
The draft amending three tax laws proposes a non-agricultural land use tax rate of 0.2% for abandoned land, land not put into use and land put into use late. Under Article 7 of the Law on Non-Agricultural Land Use Tax 2010, the current highest rate of 0.2% applies to encroached or occupied land; land not used as required is taxed at 0.15%; residential land within quota at 0.03%. The proposed rate would therefore equal that for encroached land and be almost 7 times the rate for residential land within quota.
Review committee views
The Economic and Financial Committee broadly agreed with the 0.2% rate but asked for clarity on its relationship with the 0.15% rate now applied to unused land. It noted that the draft Land Law defines abandoned land but not unused or slowly used land, while delayed projects already pay amounts under the Land Law, so two financial obligations should not be stacked on the same case.
Illustration
This is an illustrative example. A foreign-invested company leased 3 hectares in 2023 to build a factory, with construction scheduled to finish in 2025. By the end of 2026 the site has only been levelled, about 12 months behind. Under current law, the company still has time before it must seek an extension and pay. If the draft is passed, the progressive charge could start earlier, plus the 0.2% tax if the land is found to be put into use late. The company should apply now to adjust the project schedule under the Investment Law, with evidence of the reasons for delay, rather than waiting for the new law to take effect.
What to do
- Compare actual progress with the schedule in the investment registration certificate and the land allocation or lease decision.
- If already late, apply to adjust the schedule under the Investment Law (a simplified procedure applies in some cases under Decree 96/2026) without waiting for the new law.
- Keep records proving objective reasons for delay, such as late site handover or planning and construction procedure issues.
- When acquiring a project or buying into a company holding project land, check land use progress carefully, as payment obligations and recovery risk stay with the project; include a clause allocating financial liability arising from delays before the transfer date.
- Follow local land price tables and new coefficients when preparing project financial plans, as specific land pricing may be abolished.
- Watch the vote before the session closes (expected 21 November 2026) and the transitional provisions for projects already behind schedule.
Quick answers
Does delay caused by the State's late site handover count? Current law excludes force majeure, and guiding rules list some cases not counted as delay, such as late land handover by state agencies or procedural obstacles due to planning changes. Companies need documents and records to prove this; without evidence, exclusion is hard to obtain.
Does it apply to land leased with annual rent? Yes. The rules apply to land allocated and leased for projects, whether rent is paid in a lump sum or annually.
Can a project delayed by lack of funds be extended? Lack of funds is usually not treated as an objective reason. If delay stems from this, adjust the schedule early or consider transferring the project through the proper procedure.
Legal basis: Land Law No. 31/2024/QH15 (Article 81(8)); Law on Non-Agricultural Land Use Tax No. 48/2010/QH12 (Article 7); Law on Investment No. 143/2025/QH15; Decree No. 96/2026/ND-CP; Resolution No. 21-NQ/TW of 28 July 2026; the draft Land Law (amended) and the draft Law amending the Corporate Income Tax Law, the Law on Non-Agricultural Land Use Tax and the Personal Income Tax Law at the Second Session of the 16th National Assembly.
This article is general information and does not replace advice on your specific case.